Installation at depots

The installation priorities for depots are based on the criteria below.

  • Sites that are currently involved in supporting fire operations are highest priority (1)
  • Sites co-located with level 3 ICC’s
  • Sites collocated with level 2 ICC’s or division command points
  • Depots that are separate from the office locations

The following Gippsland depots sites had wifi installed as part of the initial Proof of Concept (refer landing page). These sites will have the new device configuration pushed out remotely (at a time that will be agreed and will minimise operational impacts): Orbost, Nowa Nowa, Bairnsdale, Dargo, Brigalong, Yarrram.

Back to previous page (wifi landing page)

Region Depot Installation priority Installation date Installation status
Gippsland* Bendoc 2 25/01/2020 Complete
Cann River 2 21/02/2020 Complete
Erica 1 14/02/2020 Complete
Foster 3 TBC Not started
Heyfield 1 14/02/2020 Complete
Noojee 1 14/02/2020 Complete
Barwon South West Angelsea 1 TBC Not started
Dartmoor 3 01/2020 Complete
Gellibrand 2 TBC Not started
Grampians Cavendish 2 TBC Not started
Daylesford 1 17/02/2020 Complete
Hume Alexandra 1 21/02/2020 Complete
Bright 3 05/01/2020 Complete
Broadford 2 20/12/2019 Complete
Mansfield 1 20/12/2019 Complete
Marysville 2 21/02/2020 Complete
Ovens 1 05/01/2020 Complete
Loddon Mallee Avoca 2 TBC Not started
Bendigo 1 19/12/2019 Complete
Heathcote 2 TBC Not started
Maryborough 2 TBC Not started
Rushworth 3 TBC Not started
St Arnaud 3 TBC Not started